Northwest Territories Power Corporation Home  
 


Snare hydro line repair deemed urgent

Yellowknife NT (March 4, 1999)
A major repair program to replace 270 defective cable splices on the 140 –km Snare hydro line got underway in late February, says the NWT Power Corporation.

The project, estimated to cost up to $5 million, is deemed urgent by the Corporation to restore the line’s safety and reliability. It connects Yellowknife and Rae Edzo with 30 megawatts of hydro generation from four plants on the Snare River.

The Corporation became aware there may be a problem last winter, when two splices showed signs of failure. Metallurgical tests conducted over the summer on a random sample of 16 more splices showed the problem was likely consistent across the entire system, and prompted the decision to proceed with the repair. (The problem is unrelated to interruptions caused this past winter by frost build-up on the power lines).

The cable splices are aluminum metal tubes that connect strands by heavy electrical conductor cable. During installation, these tubes are hydraulically compressed to grip the cable ends. The tests showed that none of the sample splices had been compressed to design specifications and could, over time, allow the cables to separate.

A worst-case situation could see a sudden, complete failure of a splice. The resulting whiplash effect could collapse entire sections of the line’s 368 steel transmission towers. Repairs would take months, and be extremely expensive, as the City and Rae Edzo would be powered almost entirely by diesel generation.

“The loss of this line would cut our electrical supply for up to a year”, said
Rick Blennerhassett, Vice President of Operations for the Corporation. “Because the hydro supply is absolutely vital, we can’t afford to put our system, and our customers, at that risk”.

“We are convinced that the splice problem has reduced the margin of reliability and safety to a point where we have to take action”.

The NWT Public Utilities Board has agreed the project should go ahead on reliability and safety grounds, but has deferred any decision on how to allocate the cost. That issue will be decided during public hearings, when the Corporation files its next General Rate Application likely in early 2000. The project could impact Snare system power rates to Yellowknife, Rae Edzo and Dettah by between 1.8 and 2.2. per cent.

The line was built in 1989 at a cost of $22 million, replacing a smaller, wooden pole line that dates back to 1948. Part of this older line will be restored and used to relay power from Snare while the newer line is repaired.

The project will be conducted in four phases over the next 15 months. More than 60 per cent of the cost will be spent on services in the Yellowknife economy. Under direction of the Corporation, several local firms, and one Alberta company specializing in transmission lines, have been contracted to handle helicopter, expediting and winter road clearing.